Solar Export Limits Explained: What Happens If the DNO Restricts Your System?

Solar Export Limits & G100 Explained

A Distribution Network Operator (DNO) can place a limit on how much electricity your solar panels and battery are allowed to export to the grid. But an export limit does not necessarily mean you have to install a smaller solar system.

This is an important distinction. Your solar array might be capable of generating considerably more power than you are permitted to export at any one time. With the right system design, electricity can still be used in your home and, where suitable, stored in a battery, while an export limitation scheme controls what reaches the network.

The important point: generation capacity and export capacity are not the same thing. A DNO export limit controls electricity flowing onto the grid, not necessarily the maximum amount your solar panels can generate.

Why can the DNO limit solar export?

Britain's local electricity networks were originally designed mainly to deliver power from the grid to homes and businesses. Solar panels and batteries can reverse that flow by sending surplus electricity back onto the network.

Your DNO therefore assesses whether the local network can safely accommodate the proposed generation and storage. Depending on the system and connection route, this assessment sits within the requirements commonly referred to as G98 and G99.

If unrestricted export could create a network constraint, the DNO may approve the installation subject to an agreed export limit rather than allowing the system's full potential output to reach the grid.

What is G100 export limitation?

G100 is an Energy Networks Association engineering recommendation covering customer export and import limitation schemes. In practical terms, a compliant export limitation scheme monitors power at the point where your property connects to the distribution network and controls the system so that the agreed export level is not exceeded.

This restriction is dynamic. The system monitors what your home is consuming and what your solar and battery system is producing. If export approaches the agreed limit, compatible controls can reduce generation or battery discharge as required.

The generation and storage equipment must still meet the applicable grid-connection requirements. G100 works alongside G98 or G99; it does not replace them.

Does an export limit mean wasted solar electricity?

Not automatically.

Imagine your solar panels are producing 6kW and your export is limited to 3.68kW. If your home is simultaneously consuming 2kW, only 4kW is potentially available for export before considering any battery charging. The control system responds to the net flow at the grid connection, rather than simply looking at the headline output of the solar array.

If a compatible home battery has spare capacity, some surplus solar may also be stored for later use instead of being exported.

Export restriction becomes more relevant when generation is high, household demand is low and the battery cannot absorb additional energy. At that point, the system may need to reduce output to keep grid export within the permitted limit.

Can I install more solar than my export limit?

Potentially, yes, subject to DNO approval and a correctly designed system.

This can make sense because solar panels rarely operate at their maximum rated output continuously. Generation changes with weather, season, roof orientation and shading. Our guide to solar panel generation estimates explains why kWp array size and annual kWh generation are different measurements.

A larger array can potentially produce more useful electricity during mornings, evenings, winter and cloudy periods, even if export occasionally needs to be restricted during periods of very high generation.

The correct design therefore depends on how much electricity your property consumes, when you use it, whether battery storage is included and the export capacity agreed with the DNO.

What does 'zero export' mean?

A zero-export arrangement is an extreme form of export limitation where the system is controlled so that generated electricity is not intentionally exported onto the distribution network.

This does not mean solar generation has no value. Electricity can still be consumed behind the meter by the property, and compatible battery storage may be able to absorb surplus generation. The controls must prevent the site from exceeding its approved export condition.

A worked example: an 8kW system with a 3.68kW export limit

Consider a home with solar and battery equipment capable of delivering 8kW, but an agreed maximum grid export of 3.68kW.

If the system is producing 7kW while the house is consuming 2kW and the battery is charging at 2kW, the remaining net export would be around 3kW. That is below the 3.68kW limit, so no additional restriction would be required in this simplified example.

Now imagine the battery is full and the house is consuming only 1kW while solar output remains at 7kW. Without control, around 6kW could flow to the grid. An appropriately configured export limitation scheme would need to constrain system output so that export remains within the agreed maximum.

A useful question to ask an installer: “What export capacity has been assumed in my design, and what happens to surplus solar if the system reaches that limit?”

Why export limits should be considered during design

The DNO connection should not be an afterthought. It can influence inverter settings, battery operation, export potential and ultimately the economics of the proposed system.

At Renewable Energy Service, grid connection forms part of the system-design process. We manage the relevant DNO application or notification for our installations and consider the proposed solar array, battery capacity and grid connection together.

A properly designed home solar system should therefore balance generation, household consumption, storage and the agreed network connection rather than assuming every available kilowatt can always be exported.

An export limit does not automatically mean less solar. It means the whole energy system needs to be designed intelligently around your home and its grid connection.